Holdback · Held by others
Okanagan Cold Holdings · OCS-PRIME-2025
Currently held · CAD
$11,800.00
$11,800.00 accrued
Recorded completion
Lien closes · 47d
Release eligible · 55d
Substantial completion
Jul 23, 2026
Recorded completion anchor
Lien window closes
Sep 8, 2026
45-day period · BC Builders Lien Act s. 20
Release eligible
Sep 16, 2026
55-day period · BC Builders Lien Act s. 8(1)-(2)
Released
Pending
Awaiting action
Next step
The recorded eligibility date has arrived and the lien window has closed. Confirm payment and any remaining release conditions with Okanagan Cold Holdings and record the receipt when it arrives.
The invoice and declarations supporting this release.
No release invoice linked
Link the invoice that billed this holdback to update the release schedule.
CCDC 9A / 9B payment declarations supporting this release.
Maya Chen · President
Period Apr 29, 2026 – May 29, 2026 · Generated May 30, 2026
1 invoice · $11,800.00 withheld
Issued May 30, 2026 · Paid
Invoiced
$123,900.00
Withheld
$11,800.00
Project value, contract terms and notice contact
Contact not recorded
$720,000.00 · 10.0% holdback
BC Builders Lien Act s. 8(1)-(2)
Statutory holdback becomes eligible for release 55 days after substantial completion in this project's province.
Lien claims must be preserved within 45 days of substantial completion / abandonment / contract end in this project's province.
BC's Construction Prompt Payment Act would shorten the holdback period to 46 days and abolish a standalone lien against the holdback. It received Royal Assent on 2025-11-27 but has not been brought into force and has no proclamation date, so the Builders Lien Act periods above continue to apply.