Invoice DAN-OFFICE-001Uploaded document
Sent Proper-invoice review recordedRiverbend Toronto Office RenovationDanforth Ceilings & Drywall Inc.
Money you owe
Invoice sections
Invoice in progress
- Payments
None recorded.
Deadline overview3
View allUpcoming dates and recorded outcomes. Each deadline retains its recorded triggering event.
Deficiency review window
UpcomingFlag deficiencies
Due Nov 25, 2026
Dispute window
UpcomingReview whether to give a non-payment notice
Due Dec 2, 2026
Owner payment due
UpcomingPay this invoice
Due Dec 16, 2026
Line items 2
Partition board and framing materials · +1 more
Line items (2)
- Partition board and framing materials$5,000.00
200 m² × $25.00
- Installation labour$3,500.00
1 ls × $3,500.00
| Description | Qty | Unit | Rate | Amount |
|---|---|---|---|---|
| Partition board and framing materials | 200 | m² | $25.00 | $5,000.00 |
| Installation labour | 1 | ls | $3,500.00 | $3,500.00 |
Invoice dates & delivery
- Issue date
- Nov 17, 2026
- Billing period
- Oct 28, 2026 – Nov 16, 2026
- Sent
- Not recorded
- Nov 18, 2026, 07:05 a.m. PT
- Delivery method
- Delivery reference
- Not recorded
- Contract reference
- RBO-PRIME
Notes
Confirm the measured partition quantities with the site supervisor before accepting this draw.
- Payments
No payments recorded yet.
Source and validation
- Source
- Uploaded invoice
- Invoice PDF
- Open source PDF
- Proper-invoice assessment
- Content check passed
- Recipient receipt
- Nov 18, 2026
Deadlines
Flag deficiencies
Upcoming- Due
- Nov 25, 2026, 09:59 p.m. PT
Prepare deficiency noticeWorkflowsReview the received invoice and notify the contractor in writing of any deficiencies and what is needed to address them within seven days of receipt.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
If you miss it
Without a timely, effective notification, the invoice may be deemed proper. Any resulting owner-payment period runs from the controlling receipt, not seven days later. Verify the actual communications and service records.
- Responsibility
- Your call
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Review whether to give a non-payment notice
Upcoming- Due
- Dec 2, 2026, 09:59 p.m. PT
Prepare non-payment noticeWorkflowsIf you intend to dispute this invoice, you must issue a notice of non-payment by this date.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
If you miss it
A late notice cannot establish the timely-notice exception to payment. Other contractual defences and remedies require a separate assessment.
- Responsibility
- Your call
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Pay this invoice
Upcoming- Due
- Dec 16, 2026, 09:59 p.m. PT
- Recorded amount
- $8,755.00
Record paymentWorkflowsYou owe payment by this date. After this, interest accrues and the counterparty can escalate to adjudication or lien.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- You owe
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
- Ont. O. Reg. 303/18 Form 1.1 · delivered ·$1,550.00Sent
| Direction | Form | Disputed | Delivered | |
|---|---|---|---|---|
| Sent | Ont. O. Reg. 303/18 Form 1.1 | $1,550.00 | · |
Invoice DAN-OFFICE-001 is anchored on its receipt of 2026-11-18 under Ontario's framework. 3 statutory levers remain open on this invoice.
Flag deficiencies before the invoice is deemed properyour leverNov 25, 2026Open
Runs to 2026-11-25, seven days from recorded receipt, including when the invoice has deficiencies.
Ont. Construction Act Section 6.1(2) Dispute by notice of non-paymentyour leverDec 2, 2026Open
The calculated notification period runs to 2026-12-02. Check the applicable form, grounds and service requirements before relying on a notice. One notice on this invoice has a recorded screening issue: has no valid delivery date on or before this assessment.
Ont. Construction Act Section 6.4(2) Statutory payment obligationyour leverDec 16, 2026Open
$8,755.00 falls due 2026-12-16 under Ontario's 28-day clock.
Ont. Construction Act Section 6.4(1)
SHA-256 hash
958cc0b9b12374fab4e4724d2c33c36eaaacb6117ca3d6e2e5e41165b93397a6Generated
Nov 18, 2026, 07:12 a.m. PT
Tiercord 0.7.0
Review & evidence
Computed from workspace records. Not legal advice.