Invoice PEC-2026-05-20Uploaded document
Sent Proper-invoice review recordedFalse Creek ResidencesPacific Electric Co.
Money you owe
Invoice sections
Invoice in progress
Deadline overview3
View allUpcoming dates and recorded outcomes. Each deadline retains its recorded triggering event.
Line items 2
Parkade lighting and conduit · +1 more
- Payments
No payments recorded yet.
Line items (2)
- Parkade lighting and conduit$15,900.00
1 ls × $15,900.00
- Temporary power, period$2,500.00
1 ls × $2,500.00
Invoice dates & delivery
- Issue date
- Sep 13, 2026
- Billing period
- Aug 14, 2026 – Sep 12, 2026
- Sent
- Not recorded
- Recipient receipt
- Sep 14, 2026, 09:05 a.m. PT
- Delivery method
- Delivery reference
- Not recorded
- Contract reference
- FCR-S-03
- Payments
No payments recorded yet.
Deadlines
Flag deficiencies
Upcoming- Due
- Sep 21, 2026, 11:59 p.m. PT
Issue deficiency noticeLast chance to issue a deficiency notice. Stay silent and the invoice is deemed proper, and the 28-day clock starts automatically.
Deficiency review window
A 7-day window to flag missing s. 6.1 elements on an invoice. Past this date the invoice is treated as 'proper' and the 28-day clock starts.
If you miss it
After 7 days of silence, the invoice is automatically treated as proper. The 28-day payment clock starts whether you've reviewed it or not.
- Responsibility
- Your call
- Started
- Sep 14, 2026, 09:05 a.m. PT
- Window
- 7-day window
- Statutory reference
- BC CPPA Section 7
(2) (enacted, not in force)
Decide whether to dispute
Upcoming- Due
- Sep 28, 2026, 11:59 p.m. PT
Issue noticeIf you intend to dispute this invoice, you must issue a notice of non-payment by this date.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
If you miss it
Miss this and the invoice is deemed accepted. The right to dispute is lost.
- Responsibility
- Your call
- Started
- Sep 14, 2026, 09:05 a.m. PT
- Window
- 14-day window
- Statutory reference
- BC CPPA Section 11
(2) (b) (i) (enacted, not in force)
Pay this invoice
Upcoming- Due
- Oct 13, 2026, 11:59 p.m. PT
- Recorded amount
- $17,480.00
Record paymentYou owe payment by this date. After this, interest accrues and the counterparty can escalate to adjudication or lien.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- You owe
- Started
- Sep 14, 2026, 09:05 a.m. PT
- Window
- 28-day window
- Statutory reference
- BC CPPA Section 9
(1) (a) (enacted, not in force)
- Notices of non-payment
No notices on record.
Invoice PEC-2026-05-20 is anchored on its receipt of 2026-09-14 under British Columbia's framework. 3 statutory levers remain open on this invoice. Prompt-payment dates shown here are a working model for legislation not yet in force; they are not current statutory payment obligations.
Flag deficiencies before the invoice is deemed properyour leverSep 21, 2026Open
Runs to 2026-09-21, 7 days from the recorded receipt.
BC CPPA Section 7(2) (enacted, not in force) Dispute by notice of non-paymentyour leverOct 19, 2026Open
Runs to 2026-10-19; after that the right to withhold by notice is lost.
BC CPPA Section 9(1) (b) (ii), Section 9 (2) (enacted, not in force) Statutory payment obligationyour leverOct 13, 2026Open
$17,480.00 falls due 2026-10-13 under British Columbia's 28-day clock.
BC CPPA Section 9(1) (a) (enacted, not in force)
SHA-256 hash
66d0ee39a7f7eef21310e1fd0baff0861090ddd1c3b7917ac4a01b250d1fa75eGenerated
Sep 14, 2026, 09:12 a.m. PT
Tiercord 0.7.0
Review & evidence