Riverbend Toronto Office Renovation
- Project address
- 100 King Street West
- Prime contract signed
- Sep 21, 2026
- Total project value
- $60,000.00
Ontario
In forceConstruction Act (R.S.O. 1990, c. C.30) in force since October 1, 2019.
Adjudication authority: Ontario Dispute Adjudication for Construction Contracts (ODACC).
Recent invoices
The latest billing activity on this project.
Open deadlines
3 open · earliest dates first
Flag deficiencies
UpcomingInvoice DAN-OFFICE-001
- Due
- Nov 25, 2026, 09:59 p.m. PT
Prepare deficiency noticeWorkflowsReview the received invoice and notify the contractor in writing of any deficiencies and what is needed to address them within seven days of receipt.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
If you miss it
Without a timely, effective notification, the invoice may be deemed proper. Any resulting owner-payment period runs from the controlling receipt, not seven days later. Verify the actual communications and service records.
- Responsibility
- Your call
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Review whether to give a non-payment notice
UpcomingInvoice DAN-OFFICE-001
- Due
- Dec 2, 2026, 09:59 p.m. PT
Prepare non-payment noticeWorkflowsIf you intend to dispute this invoice, you must issue a notice of non-payment by this date.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
If you miss it
A late notice cannot establish the timely-notice exception to payment. Other contractual defences and remedies require a separate assessment.
- Responsibility
- Your call
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Pay this invoice
UpcomingInvoice DAN-OFFICE-001
- Due
- Dec 16, 2026, 09:59 p.m. PT
- Recorded amount
- $8,755.00
Record paymentWorkflowsYou owe payment by this date. After this, interest accrues and the counterparty can escalate to adjudication or lien.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- You owe
- Started
- Nov 18, 2026, 07:05 a.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Contracts
Who you bill, who bills you, and the agreed terms.
- Danforth Ceilings & Drywall Inc.$60,000.00Prime · 10% holdbackMoney you owe
| Value | ||||||
|---|---|---|---|---|---|---|
| Danforth Ceilings & Drywall Inc. RBO-PRIME | Money you owe | Prime | $60,000.00 | 10% | No | Edit |