Kingsway Medical Centre
ActiveBC · Pending5230 Kingsway · Prime contract signed Jan 10, 2026 · Total value $1,650,000.00
British Columbia
Pending in forceConstruction Prompt Payment Act (SBC 2025, c. 24)
BC's Construction Prompt Payment Act received Royal Assent 2025-11-27 and is not yet in force (commencement by regulation, s. 59; none deposited). Tiercord computes BC's payment, notice and adjudication clocks from the Act as passed and flags each as pending until proclamation. Holdback and lien figures come from the Builders Lien Act, which is in force.
Lien rights extinguished
Overdue- Due
- Sep 9, 2026, 11:59 p.m. PT
The lien-filing window expired. You can no longer register a builders lien on this project. Your security for unpaid amounts is gone; you can still sue in contract for the underlying debt, but the in rem remedy against the land is lost.
Lien filing window closes
Liens must be filed within 45 days of substantial completion / abandonment / contract end. After that lien rights are extinguished.
If you miss it
Lose the right to file a builders lien on this project. Your security for unpaid amounts is gone.
- Responsibility
- Past deadline
- Started
- Jul 26, 2026, 12:00 a.m. PT
- Window
- 45-day window
- Statutory reference
- BC Builders Lien Act Section 20
Holdback eligible for release
Due soon- Due
- Sep 19, 2026, 11:59 p.m. PT
- Recorded amount
- $10,090.00
Holdback funds become eligible for release on this date. Chase if not paid.
Holdback release eligible
After the holdback period (55 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Jul 26, 2026, 12:00 a.m. PT
- Window
- 55-day window
- Statutory reference
- BC Builders Lien Act Section 8
(1)- (2)
Holdback eligible for release
Due soon- Due
- Sep 19, 2026, 11:59 p.m. PT
- Recorded amount
- $2,720.00
Holdback funds become eligible for release on this date. Chase if not paid.
Holdback release eligible
After the holdback period (55 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Jul 26, 2026, 12:00 a.m. PT
- Window
- 55-day window
- Statutory reference
- BC Builders Lien Act Section 8
(1)- (2)
Holdback eligible for release
Due soon- Due
- Sep 19, 2026, 11:59 p.m. PT
- Recorded amount
- $2,280.00
Holdback funds become eligible for release on this date. Chase if not paid.
Holdback release eligible
After the holdback period (55 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Jul 26, 2026, 12:00 a.m. PT
- Window
- 55-day window
- Statutory reference
- BC Builders Lien Act Section 8
(1)- (2)
- Kingsway Health Partners$1,650,000.00Owner · 10% holdback · stat decMoney owed to you
- Coastal Drywall Ltd.$210,000.00Sub · 10% holdbackMoney you owe
- Pacific Electric Co.$180,000.00Sub · 10% holdbackMoney you owe
- Apex Mechanical Services$160,000.00Sub · 10% holdbackMoney you owe