North York Loft Conversion
- Project address
- 212 Sheppard Ave E
- Prime contract signed
- Jul 20, 2026
- Total project value
- $350,000.00
Ontario
In forceConstruction Act (R.S.O. 1990, c. C.30) in force since October 1, 2019.
Adjudication authority: Ontario Dispute Adjudication for Construction Contracts (ODACC).
Deficiency review window
MetInvoice NYL-087
- Satisfied
- Sep 23, 20265 days early
- Due
- Sep 28, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
- Started
- Sep 21, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Deficiency review window
Met lateInvoice NYL-061
- Satisfied
- Oct 10, 20265 days late
- Due
- Oct 5, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running. This was satisfied after the deadline had passed, so anything that had already accrued or become available by then is unaffected by the late satisfaction.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
- Started
- Sep 28, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Dispute window
MetInvoice NYL-087
- Satisfied
- Sep 23, 202612 days early
- Due
- Oct 5, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Sep 21, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Dispute window
MetInvoice NYL-061
- Satisfied
- Oct 10, 20263 days early
- Due
- Oct 13, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Sep 28, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Deficiency review window
MetInvoice NYL-101
- Satisfied
- Oct 6, 20267 days early
- Due
- Oct 13, 2026, 08:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
- Started
- Oct 4, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Owner payment due
Met lateInvoice NYL-087
- Satisfied
- Oct 22, 20263 days late
- Due
- Oct 19, 2026, 08:59 p.m. PT
- Recorded amount
- $12,360.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice. This was satisfied after the deadline had passed, so anything that had already accrued or become available by then is unaffected by the late satisfaction.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Sep 21, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Dispute window
MetInvoice NYL-101
- Satisfied
- Oct 6, 202613 days early
- Due
- Oct 19, 2026, 08:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Oct 4, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Payment is past due
OverdueInvoice NYL-061
- Due
- Oct 26, 2026, 08:59 p.m. PT
- Recorded amount
- $10,094.00
Record paymentWorkflowsThe 28-day owner-payment window expired. Statutory interest is now accruing in your favour. You can refer the unpaid amount to interim binding adjudication, and your lien rights remain available within the statutory filing window. Record the payment here when it arrives.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- They owe you
- Started
- Sep 28, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Unpaid-cascade deadline
MetInvoice NYL-087
- Satisfied
- Oct 22, 20264 days early
- Due
- Oct 26, 2026, 08:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, based on the recorded payment or notice evidence. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or give a timely applicable non-payment notice, including an undertaking where required.
- Started
- Sep 21, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Adjudication materials due
MetInvoice NYL-061
- Satisfied
- Oct 29, 20261 day early
- Due
- Oct 30, 2026, 08:59 p.m. PT
- Recorded amount
- $10,094.00
WorkflowsYour materials were submitted
Your claimant materials are recorded as submitted and the materials clock is closed. The determination clock is tracked separately.
Adjudication materials due
Once an adjudicator is appointed, claimant materials must be submitted within 5 days.
- Started
- Oct 25, 2026, 09:00 a.m. PT
- Window
- 5-day window
- Statutory reference
- Ont. Construction Act Section 13.11
Pay subs even if owner hasn't paid
TodayInvoice NYL-061
- Due
- Nov 2, 2026, 09:59 p.m. PT
Review downstream noticeWorkflowsThis clock runs from the date the proper invoice was given to the owner. Pay your subs from your own funds by this date, or give a timely applicable non-payment notice, including an undertaking where required.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or give a timely applicable non-payment notice, including an undertaking where required.
If you miss it
Subs gain the same statutory remedies as if you had been paid; you also lose the s. 6.5(5) shield from liability.
- Responsibility
- You owe
- Started
- Sep 28, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Owner payment due
MetInvoice NYL-101
- Satisfied
- Nov 1, 20261 day early
- Due
- Nov 2, 2026, 09:59 p.m. PT
- Recorded amount
- $16,480.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Oct 4, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Deficiency review window
MetInvoice NYL-104
- Satisfied
- Oct 30, 20265 days early
- Due
- Nov 4, 2026, 09:59 p.m. PT
WorkflowsDeficiency window is closed
This deficiency window is closed on the record. The counterparty's opportunity to flag missing invoice elements is no longer running.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
- Started
- Oct 28, 2026, 01:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Unpaid-cascade deadline
MetInvoice NYL-101
- Satisfied
- Nov 1, 20268 days early
- Due
- Nov 9, 2026, 09:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, based on the recorded payment or notice evidence. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or give a timely applicable non-payment notice, including an undertaking where required.
- Started
- Oct 4, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
They can still flag deficiencies
UpcomingInvoice NYL-106
- Due
- Nov 9, 2026, 09:59 p.m. PT
WorkflowsThe owner has seven days from receipt to identify deficiencies in writing and explain what is needed to address them.
Deficiency review window
The owner has seven days from receipt to notify the contractor in writing of deficiencies and what is needed to address them. The period runs even if the invoice has not passed a content check.
If you miss it
Without a timely, effective notification, the invoice may be deemed proper. Any resulting owner-payment period runs from the controlling receipt, not seven days later. Verify the actual communications and service records.
- Responsibility
- They owe you
- Started
- Nov 1, 2026, 02:15 p.m. PT
- Window
- 7-day window
- Statutory reference
- Ont. Construction Act Section 6.1
(2)
Dispute window
MetInvoice NYL-104
- Satisfied
- Oct 30, 202613 days early
- Due
- Nov 12, 2026, 09:59 p.m. PT
WorkflowsDispute window is closed
This dispute window is closed on the record. It is no longer running against your invoice, and any notice of non-payment that was served is listed on the invoice.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
- Started
- Oct 28, 2026, 01:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Their non-payment notice window
UpcomingInvoice NYL-106
- Due
- Nov 16, 2026, 09:59 p.m. PT
WorkflowsThe payer has until this date to give a statutory non-payment notice for the amount it intends to withhold.
Dispute window
A 14-day window to formally dispute an invoice by issuing a notice of non-payment.
If you miss it
A late notice cannot establish the timely-notice exception to payment. Other contractual defences and remedies require a separate assessment.
- Responsibility
- They owe you
- Started
- Nov 1, 2026, 02:15 p.m. PT
- Window
- 14-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(2)
Owner payment due
MetInvoice NYL-104
- Satisfied
- Oct 30, 202626 days early
- Due
- Nov 25, 2026, 09:59 p.m. PT
- Recorded amount
- $8,858.00
WorkflowsPayment received in full
This invoice was paid in full and the 28-day owner-payment clock is closed. The payment that settled it is recorded on this invoice.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
- Started
- Oct 28, 2026, 01:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
They owe you payment
UpcomingInvoice NYL-106
- Due
- Nov 30, 2026, 09:59 p.m. PT
- Recorded amount
- $9,682.00
Record paymentWorkflowsPayment is due to you on this date. If unpaid, statutory interest accrues and adjudication is available.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- They owe you
- Started
- Nov 1, 2026, 02:15 p.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Awaiting determination
UpcomingInvoice NYL-061
- Due
- Nov 30, 2026, 09:59 p.m. PT
- Recorded amount
- $10,094.00
WorkflowsThe adjudicator's determination is expected by this date. No action needed from you unless they request more.
Determination due
The adjudicator must issue their determination within 30 days of receiving the claimant's materials.
If you miss it
Process may extend with consent; otherwise the matter can be re-referred. Tracked for awareness.
- Responsibility
- Shared
- Started
- Oct 29, 2026, 09:00 p.m. PT
- Window
- 30-day window
- Statutory reference
- Ont. Construction Act Section 13.13
Unpaid-cascade deadline
MetInvoice NYL-104
- Satisfied
- Oct 30, 202633 days early
- Due
- Dec 2, 2026, 09:59 p.m. PT
WorkflowsSub-payment obligation is discharged
This sub-payment clock is closed on the record, based on the recorded payment or notice evidence. Nothing further is outstanding on it.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or give a timely applicable non-payment notice, including an undertaking where required.
- Started
- Oct 28, 2026, 01:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)
Pay subs even if owner hasn't paid
UpcomingInvoice NYL-106
- Due
- Dec 7, 2026, 09:59 p.m. PT
Review downstream noticeWorkflowsThis clock runs from the date the proper invoice was given to the owner. Pay your subs from your own funds by this date, or give a timely applicable non-payment notice, including an undertaking where required.
Unpaid-cascade deadline
Even if the owner hasn't paid you, you must pay your subs by day 35, or give a timely applicable non-payment notice, including an undertaking where required.
If you miss it
Subs gain the same statutory remedies as if you had been paid; you also lose the s. 6.5(5) shield from liability.
- Responsibility
- You owe
- Started
- Nov 1, 2026, 02:15 p.m. PT
- Window
- 35-day window
- Statutory reference
- Ont. Construction Act Section 6.5
(4)