ActiveON · In force212 Sheppard Ave E · Prime contract signed Jun 5, 2026 · Total value $980,000.00
Ontario
In forceConstruction Act (R.S.O. 1990, c. C.30) in force since October 1, 2019.
Adjudication authority: Ontario Dispute Adjudication for Construction Contracts (ODACC).
Payment is past due
OverdueInvoice DCD-2026-04-02
- Due
- Aug 27, 2026, 08:59 p.m. PT
- Recorded amount
- $12,875.00
Record paymentThe 28-day window expired without payment or a notice of non-payment. Statutory interest is accruing against you, the counterparty may refer the matter to adjudication, and their lien rights remain available. Pay as soon as possible to limit interest and avoid escalation.
Owner payment due
Payment is due 28 days after a proper invoice is received, unless a notice of non-payment was issued within the dispute window.
If you miss it
Statutory interest begins accruing the day after; non-payment may trigger lien and adjudication remedies.
- Responsibility
- You owe
- Started
- Jul 30, 2026, 06:05 a.m. PT
- Window
- 28-day window
- Statutory reference
- Ont. Construction Act Section 6.4
(1)
Awaiting determination
UpcomingInvoice 2026-04-061
- Due
- Sep 25, 2026, 08:59 p.m. PT
- Recorded amount
- $58,200.00
The adjudicator's determination is expected by this date. No action needed from you unless they request more.
Determination due
The adjudicator must issue their determination within 30 days of receiving the claimant's materials.
If you miss it
Process may extend with consent; otherwise the matter can be re-referred. Tracked for awareness.
- Responsibility
- Shared
- Started
- Aug 25, 2026, 09:00 p.m. PT
- Window
- 30-day window
- Statutory reference
- Ont. Construction Act Section 13.13
Holdback eligible for release
Upcoming- Due
- Sep 30, 2026, 08:59 p.m. PT
- Recorded amount
- $5,820.00
Holdback funds become eligible for release on this date. Chase if not paid.
Holdback release eligible
After the holdback period (60 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Jul 31, 2026, 09:00 p.m. PT
- Window
- 60-day window
- Statutory reference
- Ont. Construction Act Section 22, Section 31
Last chance to file a lien
Upcoming- Due
- Sep 30, 2026, 08:59 p.m. PT
After this date you can no longer file a builders lien for unpaid amounts on this project.
Lien filing window closes
Liens must be filed within 60 days of substantial completion / abandonment / contract end. After that lien rights are extinguished.
If you miss it
Lose the right to file a builders lien on this project. Your security for unpaid amounts is gone.
- Responsibility
- Your call
- Started
- Jul 31, 2026, 09:00 p.m. PT
- Window
- 60-day window
- Statutory reference
- Ont. Construction Act Section 31
Holdback eligible for release
Upcoming- Due
- Sep 30, 2026, 08:59 p.m. PT
- Recorded amount
- $1,250.00
Holdback funds become eligible for release on this date. Chase if not paid.
Holdback release eligible
After the holdback period (60 days from substantial completion / certification), holdback amounts become eligible for release.
If you miss it
Funds remain held; cash flow impact only; no rights are lost.
- Responsibility
- They owe you
- Started
- Jul 31, 2026, 09:00 p.m. PT
- Window
- 60-day window
- Statutory reference
- Ont. Construction Act Section 22, Section 31
Last chance to file a lien
Upcoming- Due
- Sep 30, 2026, 08:59 p.m. PT
After this date you can no longer file a builders lien for unpaid amounts on this project.
Lien filing window closes
Liens must be filed within 60 days of substantial completion / abandonment / contract end. After that lien rights are extinguished.
If you miss it
Lose the right to file a builders lien on this project. Your security for unpaid amounts is gone.
- Responsibility
- Your call
- Started
- Jul 31, 2026, 09:00 p.m. PT
- Window
- 60-day window
- Statutory reference
- Ont. Construction Act Section 31
- Sheppard Estates Inc.$980,000.00Owner · 10% holdback · stat decMoney owed to you
- Danforth Ceilings & Drywall Inc.$140,000.00Sub · 10% holdbackMoney you owe