What Holdback Is and When You Can Ask for It

On this page
Your Holdback Has a Release Date. Do You Know It?
Key takeaways
Ontario, Alberta and Saskatchewan hold back 10% of the value of the work. Manitoba holds back 7.5%.
Since January 1, 2026, Ontario owners must release accrued holdback every year. They publish a notice within 14 days of each contract anniversary, then pay 60 to 74 days later, unless a lien has been preserved.
In Saskatchewan, holdback is due 40 clear days after a certificate of substantial performance is given. Alberta and Manitoba require it to be kept for 60 days after substantial performance or completion.
What holdback is
Holdback is money the payer keeps back from each payment on a construction job. The owner keeps it from the general contractor. The general contractor keeps it from its subs. Each sub keeps it from the trades below.
It isn't a penalty, and it isn't a sign that anything is wrong. It's there so there's money left on the table if someone down the chain files a lien. Once the time to file a lien has passed, the money is meant to flow back down.
The problem is that nobody sends a reminder. Holdback sits on the books as a receivable for months, the job moves on, and the date it could have been collected slips by. On a job with thin margins, holdback can be most of the profit.
How much is held back
The rate depends on the province where the work is done, not where your office is.
| Where the work is | Holdback | Where it's set |
|---|---|---|
| Ontario | 10% of the price of work and materials as they're supplied. A separate 10% applies to finishing work done after substantial performance. | Construction Act, s. 22(1) and (2) |
| Alberta | 10% of the value of work done and materials furnished | Prompt Payment and Construction Lien Act, s. 18(1) |
| Saskatchewan | 10% | The Builders' Lien Act, s. 34 |
| Manitoba | 7.5% of each payment | The Builders' Liens Act, s. 24(1) |
| Federal jobs | Only if your contract provides for it, and never more than the province's rate | Federal Prompt Payment for Construction Work Act, s. 12 |
On federal jobs in Ontario, Saskatchewan and Alberta, provincial rules govern most of the chain. Check which rules apply to your tier before you count anything.
When it comes back
Every province ties the release to an event: a certificate of substantial performance, completion, or abandonment. Know which event applies to your job, and when it happened. That date starts the count.
Ontario
Every year, on most contracts. Within 14 days after each anniversary of the contract date, the owner must publish a notice of annual release saying how much it will pay and when (s. 26(3)). It then pays the contractor 60 to 74 days after the notice, unless a lien has been preserved or perfected and not dealt with (s. 26(4)). The contractor pays its subs their share within 14 days of being paid, and so on down the chain (s. 26(5)–(6)).
Contracts signed before January 1, 2026. The first anniversary that counts is the second one after that date, and the first payment includes everything held back before it (s. 87.4(4)).
At the end of the job. Whatever is left is paid within 14 days after all liens that could be claimed against it have expired or been dealt with (s. 26(8)). A contractor's lien generally expires 60 days after the certificate of substantial performance is published, or after the contract is completed, abandoned or terminated, whichever comes first (s. 31(2)).
If your subcontract is certified complete. The payer may release your share once your lien period has passed (s. 25). "May" matters: it's allowed, not required.
Alberta
The owner keeps 10% for 60 days from the date a certificate of substantial performance is issued, or from completion if there's no certificate (s. 18(1)).
Work on oil and gas well sites, and work mainly involving concrete, has 90 days instead (s. 18(1.1) and (1.2)).
While a lien is registered, the owner also keeps any unpaid amount above the 10% (s. 18(2)).
Saskatchewan
With a certificate of substantial performance, holdback is paid 40 clear days after a copy of the certificate is given (s. 43(1)).
Without one, it's paid 40 clear days after the contract is completed or abandoned, whichever is earlier (s. 44).
If your subcontract is certified substantially performed, your share is paid 40 clear days after a copy of that certificate is given (s. 45).
All of these apply only if no claim of lien is registered and the money is otherwise due.
Yearly release applies only to contracts over $25 million with a schedule longer than a year, where no lien is registered and a notice of early release is given (s. 46).
Manitoba
Holdback is kept for at least 60 days after the earliest of these: a certificate of substantial performance is given, the work is completed, or the work is abandoned (s. 24(1)).
After those 60 days, the holdback is to be reduced and paid out, but not while a registered lien remains in effect (s. 25(1)). A similar rule applies when a subcontract is substantially performed (s. 25(2)).
How to ask for it
Holdback is easiest to collect when you know the date before the payer does. Five steps, for trades and the bookkeepers who keep their books:
Track holdback per contract, not as one lump. Record how much was held on each invoice. A single "holdback receivable" line hides which job is due.
Find out which event starts your count. Ask the general contractor or owner whether a certificate of substantial performance has been issued, and get a copy. If there isn't one, note the date the contract was completed. In Ontario and Saskatchewan, a contractor can ask the payment certifier to certify substantial performance (Ontario s. 32(1); Saskatchewan s. 41).
Put the release date in your calendar. Count the days for your province from that event. In Ontario, also note your contract's anniversary and watch for the owner's notice of annual release.
Check for liens. A registered or preserved lien can hold up the release. If one has been filed on the job, ask the payer how it's being dealt with.
Invoice for it, then follow up. Check whether your contract asks for a separate invoice or a statutory declaration before holdback is released. Send it on time, and follow up when the date passes.
If the money doesn't come, talk to the payer first. If that doesn't work, speak with construction counsel about your options, which can include adjudication in some provinces.
Where Tiercord helps
Tiercord keeps a holdback register for every contract. It shows what's been held, what's been released and what's still outstanding, all tied back to the invoices behind it. When you record a certificate, a completion date or a last-supply date, it works out the supported release date for that province. If the date it needs is missing, it says so instead of guessing.
It tracks dates. It doesn't search lien registries or tell you that all claims are cleared. That part still needs a check.
See it with your own jobs: Book a 20-minute walkthrough
General information only, not legal advice. Check your contract and speak with construction counsel.
Frequently asked questions
Your Holdback Has a Release Date. Do You Know It?
Key takeaways Ontario, Alberta and Saskatchewan hold back 10% of the value of the work. Manitoba holds back 7.5%. Since January 1, 2026, Ontario owners must release accrued holdback every year. They publish a notice within 14 days of each contract anniversary, then pay 60 to 74 days later, unless a lien has been preserved. In Saskatchewan, holdback is due 40 clear days after a certificate of substantial performance is given. Alberta and Manitoba require it to be kept for 60 days after substantial performance or completion.