- Adjudicator
- An adjudicator is a neutral decision-maker, appointed by the parties or a nominating authority, who issues a binding determination in an adjudication.
- Authorized nominating authority
- An authorized nominating authority is the body designated to administer construction adjudications and appoint adjudicators when parties cannot agree.
- Construction adjudication
- Construction adjudication is a fast, interim-binding process in which an adjudicator decides a payment dispute on a short statutory timetable.
- Construction lien
- A construction lien (builders' lien in some provinces) is a charge on improved land securing payment for work or materials, valid only if preserved in time.
- Deemed proper invoice
- A deemed proper invoice is an invoice that becomes a proper invoice by operation of law because the payer did not raise a defect within a short review window.
- Interim-binding determination
- An interim-binding determination is an adjudicator's decision that must be obeyed immediately but can still be revisited later by a court or arbitrator.
- Notice of non-payment
- A notice of non-payment is the document a payer must deliver within the dispute window to refuse all or part of a proper invoice, with specific reasons.
- Pay-when-paid
- Pay-when-paid is a contract clause tying a contractor's duty to pay its subcontractors to first being paid by the owner. Prompt-payment law restricts it.
- Payment certifier
- A payment certifier is the person, often the architect or engineer, authorized under a contract to certify the value of work for payment.
- Prompt payment
- Prompt payment is a statutory framework that makes construction payments flow down the chain on fixed deadlines, replacing open-ended pay-when-paid practice.
- Proper invoice
- A proper invoice is a written request for payment containing the information the statute and the contract require. It starts the owner-payment clock.
- Statutory holdback
- Statutory holdback is a share of each construction payment (commonly 10%) retained to protect lien claimants and released after the lien period expires.
- Substantial performance
- Substantial performance is the point at which a construction contract is essentially complete and ready for use, triggering holdback release and lien deadlines.
- Tamper-evident audit trail
- A tamper-evident audit trail is a chained record of compliance events secured so that any later alteration of the history is detectable.