Construction Holdback Rules in British Columbia

Under the Construction Prompt Payment Act, SBC 2025, c. 24

British Columbia requires a statutory holdback of 10% of each payment (BC Builders Lien Act s. 8(1)-(2)), retained rather than paid out, to protect lien claimants further down the chain. It is a standing obligation that runs alongside the prompt-payment clock, not a payment dispute.

In British Columbia the holdback is held for 55 days before it can be released, tied to substantial performance and the expiry of the lien-filing window.

BC's Construction Prompt Payment Act received Royal Assent 2025-11-27 and is not yet in force (commencement by regulation, s. 59; none deposited). Tiercord computes BC's payment, notice and adjudication clocks from the Act as passed and flags each as pending until proclamation. Holdback and lien figures come from the Builders Lien Act, which is in force.

British Columbia holdback deadlines

The statutory clocks for this topic in British Columbia, with section citations.

ClockValue
Holdback retained
Percentage of each payment retained as statutory holdback to protect lien claimants.
BC Builders Lien Act Section 8(1)-(2)
10%
Holdback release period
Period that must run before holdback may be released.
BC Builders Lien Act Section 8(1)-(2)
55 days

How much, and from what

British Columbia fixes the holdback at 10% of the value of the work or materials, taken from each payment as the work proceeds. The held-back amount accumulates over the life of the contract.

How long BC holds it

Holdback in British Columbia is retained for 55 days (BC Builders Lien Act s. 8(1)-(2)), running until the lien-filing window of 45 days (BC Builders Lien Act s. 20) has expired with no liens outstanding. Releasing it early can expose the payer to paying twice if a valid lien is later filed.

Releasing holdback

Once the British Columbia lien period has run and no liens are registered, the holdback can be released. Tiercord tracks the holdback balance and the release date for each contract and surfaces both on the deadline dashboard.

A note on status

British Columbia's prompt-payment framework is not yet in force, but that does not touch the figures on this page. The holdback percentage, the holdback period and the lien window all come from the Builders Lien Act (SBC 1997, c. 45), which is in force today and applies whether or not prompt payment has been proclaimed. It is the payment, notice and adjudication deadlines on the other BC pages that Tiercord computes as clearly-flagged working assumptions.

Holdback in British Columbia: FAQ

How much holdback must I retain in British Columbia?

10% of the value of the work or materials (BC Builders Lien Act s. 8(1)-(2)), taken from each payment.

How long is holdback held in British Columbia?

55 days (BC Builders Lien Act s. 8(1)-(2)), until the 45-day lien-filing window expires with no outstanding liens.

See the full British Columbia guide