BC Prompt Payment Act: Deadlines & Adjudication

British Columbia passed the Construction Prompt Payment Act in 2025. It received Royal Assent on November 27, 2025 but is not yet proclaimed in force, and the prescribed forms are pending in regulation. BC's current Builders Lien Act continues to govern lien and holdback rights. The uncommenced prompt-payment rules are preparation guidance, not operative payment obligations.

BC remains available in Tiercord with pending prompt-payment dates clearly identified. Its in-force lien and holdback rules remain distinct from the uncommenced prompt-payment legislation.

BC's Construction Prompt Payment Act received Royal Assent 2025-11-27 and is not yet in force (commencement by regulation, s. 59; none deposited). Tiercord computes BC's payment, notice and adjudication clocks from the Act as passed and flags each as pending until proclamation. Holdback and lien figures come from the Builders Lien Act, which is in force.
Governing statute

Construction Prompt Payment Act

SBC 2025, c. 24

In force

Not yet proclaimed

Enacted, awaiting regulations

Adjudication authority

To be designated

British Columbia prompt-payment deadlines at a glance

Each clock below runs from the event its own section names, computed in British Columbia's local time with statutory rollover for the province's holidays. Every row cites the section it comes from, where the province has one.

ClockValue
Owner payment due
Days from a proper invoice until the owner must pay or deliver a notice of non-payment.
BC CPPA Section 9(1)(a) (enacted, not in force)
28 days
Notice of non-payment window
Window to dispute an invoice. Miss it and the amount is generally payable in full.
BC CPPA Section 11(2)(b)(i) (enacted, not in force)
14 days
Deemed-proper review window
If the payer does not flag a defect in the invoice, it is deemed a proper invoice.
BC CPPA Section 7(2) (enacted, not in force)
7 days
Pay your subcontractors
After being paid, days to pass payment down to subcontractors.
BC CPPA Section 9(1)(b)(i) (enacted, not in force)
7 days
Pay subs even if unpaid
If the owner has not paid, subs must still be paid by this day when you are the contractor billing the owner, or 42 days when you are a subcontractor paying your own subcontractor, or the matter referred to adjudication.
BC CPPA Section 9(1)(b)(ii), Section 9(2) (enacted, not in force)
35 days
Undertaking to adjudicate
When refusing to pass payment down, the payer must undertake to refer the dispute to adjudication within this window.
BC CPPA Section 11(1)(b)(ii) (enacted, not in force)
21 days
Adjudication referral window
Time after the contract is complete to refer a dispute to adjudication. Refer later and the referral is a nullity.
BC CPPA Section 19(2) (enacted, not in force)
90 days after completion
Adjudicator determination
Days for the adjudicator to issue a binding determination after receiving the claimant's documents.
BC CPPA Section 30(1)(b) (enacted, not in force)
30 days
Comply with determination
Days to pay an amount ordered by an adjudicator.
BC CPPA Section 34 (enacted, not in force)
15 days
Holdback retained
Percentage of each payment retained as statutory holdback to protect lien claimants.
BC Builders Lien Act Section 8(1)-(2)
10%
Holdback release period
Period that must run before holdback may be released.
BC Builders Lien Act Section 8(1)-(2)
55 days
Lien filing window
Days to preserve or register a construction lien before the right expires.
BC Builders Lien Act Section 20
45 days

Go deeper on British Columbia

British Columbia prompt-payment FAQ

Is the BC Construction Prompt Payment Act in force?

Not yet. The CPPA (SBC 2025, c. 24) received Royal Assent on November 27, 2025 but has not been proclaimed in force, and the regulations defining the prescribed forms are still pending. Its uncommenced prompt-payment dates must not be treated as current statutory payment obligations.

What should BC contractors do now?

Keep proper invoice and service records, follow your current contract, and preserve rights under the in-force Builders Lien Act while preparing for commencement.

When does the prompt-payment clock start?

It starts when a proper invoice is received by the payer. If the invoice is missing required information, it may not qualify as a proper invoice and the clock may not start until the defect is cured.

What happens if a notice of non-payment is late?

A late notice is generally treated as if no notice was given, so the full invoiced amount becomes payable, usually with interest from the date payment was due.