Construction Lien Deadlines in British Columbia

Under the Construction Prompt Payment Act, SBC 2025, c. 24

A builders' lien secures payment for work or materials against the improved land in British Columbia, but only if it is preserved within 45 days (BC Builders Lien Act s. 20). Miss that window and the right to lien is lost, no matter how strong the underlying claim.

British Columbia's lien window is one of the deadlines Tiercord derives for every contract and surfaces alongside the prompt-payment clocks.

BC's Construction Prompt Payment Act received Royal Assent 2025-11-27 and is not yet in force (commencement by regulation, s. 59; none deposited). Tiercord computes BC's payment, notice and adjudication clocks from the Act as passed and flags each as pending until proclamation. Holdback and lien figures come from the Builders Lien Act, which is in force.

British Columbia construction liens deadlines

The statutory clocks for this topic in British Columbia, with section citations.

ClockValue
Lien filing window
Days to preserve or register a construction lien before the right expires.
BC Builders Lien Act Section 20
45 days

What a lien secures

A builders' lien attaches to the owner's interest in the land that was improved. If the claim is not paid, it can ultimately be enforced through sale of that interest, and the 10% statutory holdback fund is the first source the law looks to in order to satisfy it.

The British Columbia filing deadline is strict

A builders' lien must be preserved or registered within 45 days (BC Builders Lien Act s. 20), measured from a triggering event such as substantial performance, completion, or the last day work or materials were supplied. British Columbia courts apply the window strictly.

Liens and prompt payment work together

Prompt payment governs when money must move in British Columbia; the builders' lien and holdback secure the money if it does not. A complete compliance posture tracks all three at once.

Construction liens in British Columbia: FAQ

How long do I have to file a builders' lien in British Columbia?

45 days (BC Builders Lien Act s. 20) from the triggering event.

What triggers the lien deadline in British Columbia?

Usually substantial performance or completion of the contract, or the last day on which the claimant supplied work or materials, depending on the role of the claimant.

See the full British Columbia guide

Every deadline, notice and adjudication rule in one place.

British Columbia overview